Construction Daily Report Template and Site Diary

Record who worked on site, which equipment ran and what held the job up, and the calculator totals the man-hours worked and lost. The same layout comes as a blank Excel daily report with a weekly summary.

Calculator

Your entries stay in this browser (local storage) and are not sent anywhere.

Inputs
Weather
Units
Crews

No rows yet.

Equipment

No rows yet.

Delays

No rows yet.

Work performed

No rows yet.

Deliveries

No rows yet.

Visitors and instructions

No rows yet.

Incidents and near misses

No rows yet.

Result

Add the first row and the result appears here.

Download this calculation

This tool is an aid. It does not replace the contract, the regulations or the supervising engineer.

Blank construction daily report template

The workbook has a daily report sheet, a weekly summary that carries the running total since the start of the site, and an instructions sheet. Formulas sit in locked, shaded cells.

Download the daily report template (.xlsx)

File: construction-daily-report-template.xlsx. Excel workbook (.xlsx) with formulas and no macros; it opens in Excel, LibreOffice and Google Sheets.

The tools and templates are aids for planning and record keeping. They do not replace your contract, the applicable regulations or the supervising engineer.

Worked example: three crews and one rain delay

Formwork, steel fixing and concrete crews on site, with rain stopping 14 people for two and a half hours. These are the inputs of our calculation test.

  1. Gross man-hours: formwork 8 workers × 9 h = 72 h, steel fixing 4 × 8 h = 32 h, concrete 6 × 9 h = 54 h, together 158 h.
  2. Man-hours lost to the delay: 14 affected workers × 2.5 h = 35 h.
  3. Effective man-hours: 158 h − 35 h = 123 h.
  4. Utilization: 123 / 158 × 100 = 77.848 %, shown as 77.85 %.

Result: 158 gross, 35 lost and 123 effective man-hours, utilization 77.85 %. The tower crane on the same day logs 7 working and 2 idle hours.

How the daily report is calculated

All totals come from the crew and delay lines you enter; nothing is estimated.

Gross man-hours
H = Σ (workers × hours) over all crews

Every crew line counts once: the number of workers times the hours each of them worked.

Lost man-hours
L = Σ (affected workers × delay hours)

Each delay line is checked on its own: it cannot affect more people than were on site or last longer than the longest shift.

Utilization
U = (H − L) / H × 100

Shown as n/a when no workers are entered, because there is nothing to divide by.

What goes into a daily report

The sections of the calculator and of the Excel template, in the order you fill them in.

SectionWhat to enterWhy it matters
Date and siteDate, project or site nameTies every other entry to one day
WeatherTemperature morning, noon and evening, precipitation, windSupports a later claim that weather stopped work
CrewsCompany, trade, number of workers, hours per workerGross man-hours and the labor record
EquipmentType, number, working and idle hoursPlant time for daywork or delay claims
DelaysReason, affected workers, hoursLost man-hours and utilization
Work performedOne line per activity and locationProgress record
DeliveriesWhat arrived and how muchCross-check with delivery tickets
Visitors and instructionsWho came and what was instructedRecord of instructions given on site
Incidents and near missesYes or no, short descriptionSafety record; report through your own system as well
  • Signature fields: site manager, and the supervising engineer or client representative where your contract asks for a countersignature.

Guide

Is a site diary or daily report required?

There is no single rule for every English-speaking market, so check the contract first and the local regulations second. The record also goes by different names: site diary in the UK, Ireland and Australia, construction daily report or daily log in the US. On Canadian projects, use the term your contract uses.

CDM 2015 (SI 2015/51) sets duties for planning and managing health and safety on construction work, but we found no duty in it to keep a document called a site diary. Several things it does require overlap with a daily record: a construction phase plan and a health and safety file (regulation 12), site induction (regulations 13(4) and 15(9)(a)), an inspection of excavations at the start of every shift and after events that could affect them (regulation 22(4)), and a written report of such an inspection within 24 hours, kept on site until the work is complete and then for three months (regulation 24).

Beyond that, the site diary is a contract and evidence record. Whether your JCT or NEC contract, or the client's own conditions, ask for daily records, and who receives them, is a question for that document; we do not quote clauses here.

On US projects the construction daily report is a common project document. Whether it is required, and on which form, depends on the owner's contract and the contractor's own procedures; we have not reviewed federal or state rules on daily reports, so none is cited. The same goes for Australian and Irish projects: the contract and the project procedures decide.

How to keep a daily report that holds up later

Fill it in on the day, at the end of the shift, while names, hours and times are still known. A record written up days later carries less weight when a delay or a daywork claim is disputed.

Work through the sheet in order: weather in the morning, at noon and in the evening; one line per crew with company, trade, number of workers and hours; equipment with working and idle hours; then every delay with its reason, the number of workers it stopped and for how long. Add the work performed by location, deliveries, visitors and instructions received, and any incident or near miss.

Keep descriptions factual. "Rain 10:00 to 12:30, slab pour stopped, 14 workers stood down" is more useful than "bad weather". Record each instruction with the name of the person who gave it.

Sign the report and, where your contract asks for it, have it countersigned by the client representative or the supervising engineer. File the signed copy and keep the spreadsheet; the weekly summary sheet of the template adds up the days, so you can see the man-hours since the start of the site.

The calculator runs in your browser: names, hours and notes you type are not sent to us, and the Excel file stays on your computer.

Man-hours, utilization and common mistakes

Gross man-hours are the sum of workers times hours for each crew. Lost man-hours are the affected workers times the length of each delay. Effective hours are gross minus lost, and utilization is effective divided by gross. In the worked example, 158 gross hours less 35 lost hours leave 123 effective hours, a utilization of 77.85 %.

Utilization here is a site record, not a productivity measure: it says how much of the paid time was available for work, not how much work was done in it.

  • More affected workers than workers on site: the calculator stops with an error, because the lost hours would belong to nobody.
  • A delay longer than the longest shift of the day: also an error; split a delay that runs into overtime into separate lines.
  • Two delays that stop the same people: allowed, since each line is checked on its own, but all delays together cannot lose more hours than were worked.
  • No workers entered: man-hours are zero and utilization is shown as n/a instead of a misleading 0 %.
  • Equipment hours are machines times hours and are kept apart from labor; idle equipment does not reduce labor utilization.

Questions about construction daily reports

What should a construction daily report include?

At minimum the date, the weather, crews with workers and hours, equipment, delays with their reasons, work performed, deliveries, instructions received and incidents. Those are the sections of our template. Your contract or the client may ask for more, such as photos, test results or the names of visitors; add them as extra lines instead of leaving them out.

Is a site diary a legal requirement in the UK?

We found no duty in CDM 2015 to keep a document called a site diary. The regulations do require written reports of excavation inspections, site induction and a construction phase plan, and your building contract may require daily records. So check your contract, and keep a diary anyway: a record made on the day is strong evidence of what happened.

Is a site diary the same as a daily report?

In practice both describe the same thing: a dated record of labor, equipment, weather and events on site. Site diary is the usual term in the UK, Ireland and Australia, construction daily report or daily log in the US. Some firms keep one diary per site and separate reports per subcontractor; the template works for either, one sheet per day.

Who should fill in and sign the daily report?

Usually the person running the site that day, the site manager or the foreman, fills it in at the end of the shift. Where the contract asks for it, the client representative or supervising engineer countersigns. The template has both signature fields. At the start of the job, agree on who signs and how quickly, because an unsigned report is easier to dispute.

Is anything I type sent to you?

No. The calculator runs in your browser, and the names, hours and notes you enter are not sent to our server or stored by us. The Excel template works offline on your own computer. If the computer is shared, close the page or delete the downloaded file when you are done, as you would with any other site record.