Punch List Template and Snagging List

List every defect found at the walk-through with its location, trade, due date and status, and the calculator counts what is open, closed and overdue. The same list comes as a blank Excel punch list template.

Calculator

Your entries stay in this browser (local storage) and are not sent anywhere.

Inputs
Items

No rows yet.

Result

Add the first row and the result appears here.

Download this calculation

This tool is an aid. It does not replace the contract, the regulations or the supervising engineer.

Blank punch list template

One row per defect with drop-down lists for priority and status, overdue rows highlighted by date, a summary sheet and an instructions sheet.

Download the punch list template (.xlsx)

File: punch-list-template.xlsx. Excel workbook (.xlsx) with formulas and no macros; it opens in Excel, LibreOffice and Google Sheets.

The tools and templates are aids for planning and record keeping. They do not replace your contract, the applicable regulations or the supervising engineer.

Worked example: 20 items at a walk-through

Twenty defects across five trades, checked on an inspection date of 10 Nov 2026. These are the inputs of our calculation test.

  1. Status: 12 items open, 6 fixed and 2 accepted, so 8 closed.
  2. Share closed: 8 / 20 × 100 = 40 %.
  3. Overdue: three open items were due on 5, 8 and 9 Nov 2026, before the inspection date. One open item is due on 10 Nov 2026 itself and is not overdue yet.
  4. Estimated cost of open items: 120 + 80 + 200 + 150 + 60 + 45.50 + 45.50 + 90 + 300 + 75.25 + 30 = 1,196.25. One open item has no estimate; it counts as 0 and the calculator warns about it.

Result: 20 items, 12 open, 8 closed (40 %), 3 overdue, and open defects estimated at 1,196.25 in your currency.

How the punch list is counted

Every count uses the status and due date of each item on the inspection date you enter.

Closed share
C = (fixed + accepted) / total × 100

Fixed means the trade reports it done; accepted means the client side has checked it. Both count as closed.

Overdue
overdue = status open and due date < inspection date

An item due on the inspection date itself is not overdue. An item without a due date is never overdue.

Open cost
K = Σ estimated cost of open items

Items without an estimate count as 0, and the calculator says how many there are.

Status values and what they mean

StatusWho sets itMeaningCounted as
OpenWhoever records the defectFound at the walk-through, not yet fixedOpen; overdue once the due date has passed
FixedContractor or tradeReported as fixed, not yet checkedClosed
AcceptedClient side or supervising engineerFix checked and acceptedClosed

The same list under different names

TermWhere you hear itWhat it refers to
Punch listUS, also AustraliaThe list of incomplete or defective work as a project nears completion
Snagging list, snag listUK and IrelandThe same list; snagging also names the inspection that produces it
Defects listAustraliaThe same list in contract wording
Practical completion, rectification periodJCT contracts (UK)The completion stage, and the period after it for putting defects right
Defects dateNEC contracts (UK)The contract date that closes the period for notifying defects
  • Periods and procedures come from your contract; this table explains the terms only.

Guide

Handover and defects: what the contract decides

We do not cite a statute for punch lists in any market: in the sources we use, the punch list is a contract procedure. The list is drawn up as the work approaches completion, the contractor fixes the items and the client side checks them. What triggers the walk-through, how long the contractor has for each item and what happens to payment is written in your contract, not in the list.

On UK projects under JCT contracts, the snagging list usually comes up around practical completion, and defects that appear later are dealt with in the rectification period. NEC contracts work with a defects date instead. The length of these periods and the notice procedure are set in each contract, and we do not quote clauses.

In the US, the punch list is prepared as the project nears completion; how closing it out affects the final payment depends on the owner's contract. In Australia you will also hear defects list. In Ireland the UK term snagging is common. Whatever the name, the list supports the handover documents your contract requires and does not replace them.

How to run a walk-through and keep the list moving

Walk the building in a fixed order, room by room or grid line by grid line, with the trade foremen present if you can. Give each defect one line: where it is, which trade owns it, what is wrong in a few plain words, and a photo number if you take pictures.

Set a priority and agree on a due date with the trade before you leave the room. A list without dates cannot show what is overdue, and an item without an owner tends to stay open.

Update the status as the work is done: the trade marks an item fixed, and the client representative or supervising engineer marks it accepted after checking. Do not delete closed rows; the closed items are your record of what was put right and when.

Count again on each inspection date. The calculator and the Excel template both compare due dates with the inspection date you enter, so the overdue figure reflects the day of the check, not the day you happen to open the file.

If the client side walks the building separately, merge both lists before you issue them, so that each defect appears once and has one owner. Send the updated list to the trades after each walk-through, and file a signed copy with the handover documents.

Counting rules and common mistakes

The closed share is fixed plus accepted items divided by all items. In the worked example, 6 fixed and 2 accepted out of 20 items give 40 % closed. An item is overdue only while it is open and its due date is earlier than the inspection date, which is why the item due on the inspection day itself does not count.

Priorities help when the list is long: high for anything that affects safety, use or the handover date, medium for visible defects, low for cosmetic touch-ups. The calculator and the summary sheet total open items, overdue items and open cost per trade and per priority, so you can see which subcontractor is holding up the handover.

  • Several defects on one line: the counts look better than the building does. Split them.
  • Closing an item when the trade says it is done: use fixed until someone has checked it, then accepted.
  • Using today as the reference date: an old list opened later would show everything overdue. Enter the inspection date.
  • Missing cost estimates: they count as 0, so the open cost is a lower bound until every open item has an estimate.
  • Treating the estimated cost as a deduction: whether the client may hold back money for open defects, and how much, depends on the contract and the law where the site is.

Questions about punch lists

What is a punch list in construction?

A punch list is the list of work that is incomplete or not to the required standard when a project, or part of it, is nearly finished. The client side and the contractor walk the job, record each item with its location and the trade responsible, and the contractor works through the list until every item is fixed and accepted.

What is the difference between a punch list and a snag list?

None in substance. Punch list is the usual US term; snag list or snagging list is used in the UK and Ireland, and defects list in Australia. Snagging also names the inspection itself. The template uses the same columns for all of them: location, trade, defect, priority, responsible person, due date and status.

When does a punch list item count as overdue?

When it is still open and its due date is earlier than the inspection date you enter. An item due on the inspection day itself is not overdue yet, and an item without a due date is never counted as overdue. Fixed and accepted items are not overdue, whatever their date, because they are closed.

Who closes a punch list item?

The trade or contractor marks an item fixed when the work is done. The client representative or supervising engineer checks it and marks it accepted. Both count as closed in the totals, but keeping the two statuses apart shows which fixes are still waiting for a check before the list can be signed off.

Does a punch list replace the handover certificate?

No. The punch list is a working document. Completion, handover and the start of any defects period are set by your contract and recorded in the documents it requires. Keep the signed list with those documents as a record of what was outstanding at handover and what was put right afterwards.